MORE Power Iloilo 2024 Updates: More Electric and Power Corporation (MORE Power Iloilo) President and Chief Executive Officer Roel Castro bares development updates as the distribution utility reaches its fourth year in operation.
The monthly average interruption frequency decreased by 84% and the monthly average duration by 76% from 2021 to 2023. System Loss reduced significantly by December 2020 (18.98%), December 2021 (9.68%), and December 2022 (7.11%) since the distribution utility started its operation in March 2020 (with system loss at 30%).
Captive customers significantly increased: residential (from 55,530 in 2020 to 88,158 in 2023) and commercial (from 2,475 in 2020 to 2,606 in 2023), among others. This brings the cumulative captive market (including power and others) from 59,949 in 2020 to 93,370 in 2023.
A total of 4,883 poles were replaced and installed; 993 distribution transformers were replaced and installed; 42,823 total kWh meters were replaced; 45 automatic circuit reclosers were installed; 22 load bread switches were installed; several primary and secondary lines uprated; all from March 2020 to December 2023.
New Control Center
MORE Power New Control Center, located along Diversion Road in Iloilo City, is a response to the need for a ‘real-time operations and monitoring system to balance the power system’. It will be able to operate and monitor operations in real time.
Moreover, the new control center houses the first-ever centralized Supervisory Control and Data Acquisition (SCADA) System in Iloilo and Panay.
The SCADA System, according to Castro, is a ‘harmony of software, hardware, and intelligent programming that allows the monitoring, control, data recording, and forecasting of the system. It serves as the brain’.
Its features include the following:
Remote Substation Operations. This enables the control center to remotely access circuit breakers and switches of all substations without the need for manual intervention. This will reduce time in switching feeders after a scheduled or unscheduled shutdown.
Automated Data Recording. This enables the automated recording of data (voltage, current, frequency, and power) in millisecond intervals. These are then consolidated, analyzed, and processed to produce a systematic state of the system report.
Instantaneous Fault Detection. The system enables immediate fault detection and reduces downtime caused by manual processes. According to MORE Power, time reduction is estimated to be at 90%.
24/7 Helpline. The system also assists in improving customer service – calls and complaints are logged in by the system. This will improve turn around time in serving customers. Apart from this, the SCADA System also provides Predictive Maintenance Analysis and aids in Optimized Energy Sourcing.
“We will make use of the best technologies to assure our customers of the benefits because we at MORE Power recognize that a city that is rapidly developing cannot run anymore on a distribution system with conventional, manual methods,” states Castro.
Update at of June 2024: MORE Power E-Billing Promo Grand Prize Winners. More Electric and Power Corporation (MORE Power) successfully held the grand draw for its e-billing promotion, celebrating the transition to digital billing with impressive prizes. The draw awarded 50 winners with P500 worth of gift certificates, 20 winners with P1,000 worth of gift certificates, one winner with an e-bike, and one grand prize winner with an e-4wheel vehicle.
The grand prize winner of the e-4wheel vehicle shared her excitement and appreciation. “Antes ko nabal-an nga ako ang nagdaug sang e-4wheel vehicle, ginamanifest ko na gid ini nga magbakal para kay Mama ko para may masakyan sya kon magpaninda. I’m so happy nga ang gina manifest ko na-materialize gid sang MORE Power,” said Joy Barredo of Salas Real, Tacas, Jaro.
Before converting to e-billing, Barredo shared her frustration, especially as she is frequently out of town. “Damo ako na-miss nga mga billing ko kay wala ako di pirmi sa balay. Pirmi lang nagakadula. Actually, a lot of struggle gid ya. Pirmi lang ako late magbayad.”
When she saw MORE Power’s e-billing promotion on Facebook, she was eager about the convenience it offered. “Damo ko mga benefits, number 1 very convenient gid, mabal-an ko na dayon kon san-o ang due date ko. Bisan tungan gab-i pwede ko ya makabayad bill. Dako gid ya nga help para sa akon nga working professional. Wala na rason nga mag past due ako.”
Another e-billing winner, Philip Jude Gelilang of Balabago, Jaro, also expressed his relief and satisfaction with the e-billing service. “Kis-a indi matultulan sang mail man ang akon balay. So, wala ako idea kon pila akon nga bill. Most of the time ginabilin sang mailman ang akon bill sa akon neighbor and by that time, due na akon nga bill. Tapos kon kaisa, ginabilin lang sa gate namon, so kon mag-ulan, basa gid sya. Naga-chat nalang ako sa Facebook sang MORE Power, ginaforward man nila.”
Gelilang didn’t hesitate to register for e-billing when he saw it on MORE Power’s Facebook page. “May ara na ako nga peace of mind nga every month maabot ang akon nga bill kag once makita ko na ang akon bill, mabudget ko na ang akon nga sweldo kag ma-allocate ko ang akon mga kwarta sa iban ko nga mga balayran.”
“I was shocked when I won the e-bike. I double-checked on MORE Power’s Facebook page, and once confirmed, I shared my joy on Instagram and Facebook,” Gelilang added.
MORE Power’s e-billing service has not only made billing more convenient for its customers but also promoted environmental sustainability by reducing paper usage. The company’s commitment to enhancing customer experience through innovative solutions has been well received, as evidenced by the positive feedback and participation in the e-billing promo.
Update at of June 2024: MORE Power to Reduce Scheduled Power Interruption Hours on Weekends. As MORE Power approaches its 5th year of rehabilitation activities since beginning operations in 2020, the duration of scheduled power interruptions on weekends will be reduced from 12-13 hours to 8 hours.
Engr. Bernard Bailey Del Castillo, Vice President for the Network Development and Operations Group, stated that the remaining rehabilitation work can now be completed within a maximum of 8 hours on weekends, sparing consumers from experiencing half a day of power interruptions.
“We understand the inconvenience that our consumers have faced with 12-13 hour power interruptions almost every week. That’s why, starting in July 2024, we will shorten the duration of scheduled power interruptions,” said Del Castillo. Del Castillo also assured customers that they will be informed 3-4 days in advance of any scheduled power interruptions to allow for adequate preparation.
“Although the Magna Carta for Residential Electricity Consumers states that customers should be informed of scheduled power interruptions 48 hours prior to the scheduled power interruption, at MORE Power, we are committed to notifying our consumers 3-4 days in advance, giving them ample time to plan their weekends,” Del Castillo added.
The operations head emphasized that not all scheduled power interruptions are initiated by MORE Power. Several requests come from the National Grid Corporation of the Philippines (NGCP), which typically require 12-13 hours. MORE Power takes advantage of NGCP’s scheduled maintenance works to avoid wasting the long hours of no power in its franchise area. During weekend power interruptions, MORE Power provides affected customers with free mobile charging and water, especially during the summer when water is scarce.
Del Castillo reiterated that the rehabilitation of facilities to modernize the power grid cannot be done overnight and has taken years to achieve significant progress, “When we took over, almost all of the electrical facilities throughout the city were either defective or obsolete, requiring the replacement of nearly everything. While we conduct preparatory work through live line method without interruptions on weekdays, kailangan talaga natin na magkaroon ng brownout on weekends para makuha ang mga lumang poste and as we finalize the setup to ensure the safety of our linemen.”
In four years of powering Iloilo City’s future, MORE Power has invested heavily in infrastructure upgrades to improve distribution services and drive progress in the city. This includes the 33MVA Diversion Substation, the 30/36 MVA Megaworld Substation, 10/12.4 MVA and 30/36 MVA mobile substations which serve as temporary backups during the total rehabilitation of land-based substations.
MORE Power has replaced and installed over 7,000 poles, installed 45 automatic circuit reclosers and 22 load break switches to isolate and immediately restore power during momentary faults, purchased modern testing equipment, and is working on the ongoing underground distribution system along Calle Real.A total of approximately 50 circuit kilometers of lines were replaced and reconductored with tree wire from 2022 until the end of June 2024. These tree wires are insulated primary lines designed to prevent power interruptions caused by animal intrusion and vegetation.
MORE Celebrates 100,000th Customer
Janneth Dela Cruz, a 50-year-old cook and baker from Brgy. Mansaya, Lapuz, Iloilo, is the 100,000th customer of MORE Power, Iloilo City’s sole power distributor. Dela Cruz received an unexpected gift package to mark this significant milestone. The company’s team, led by Ms. Ma. Cristina Cabalhin, VP for Customer Care and Marketing, personally delivered a range of gift appliances to Janneth’s home, which include an oven, dough mixer, rice cooker, electric fan, washing machine, and more. Additionally, she also received groceries and baking supplies, gift certificates and cash for home repairs to further assist her in her livelihood and house repair expenses.
“Maraming-maraming salamat po, sa dami po namin, ako pa po yung napili. Salamat talaga MORE Power, Salamat din po sa President kay Sir Roel Castro po, salamat po talaga. Thank you talaga sa staff sang MORE at ako ang napili ninyo,” Dela Cruz states.
“Siya lang na gabaka-baka ubra, tatlo man lang kabataan ya. Madamu gid nga Salamat sa MORE Power ilabi na gid sa ila staff, ilabi na gid sa nagdul-ong,” says Simonia Gioneo, mother of Dela Cruz.
In just over four years since taking over as Iloilo City’s distribution utility in February 2020, MORE Power has achieved a remarkable cumulative growth rate of approximately 59.8%, expanding its customer base from over 62,000 to 100,000. This milestone reflects the company’s firm commitment to customer satisfaction and service excellence, which has been driven by innovative, customer-centric programs like the MORE Konek Program.
“Our growth is a testament to the trust and support we’ve built within the Iloilo community,” said Roel Castro, President and CEO of MORE Power. “We are dedicated to enhancing our services and ensuring that our customers feel valued every step of the way,” he adds.
Reaching 100,000 customers is a significant accomplishment for MORE Power, and as a way to celebrate this, President and CEO Roel Castro envisioned a special “pasasalamat” package for the 100,000th customer. This gesture reflects the company’s commitment to recognizing and appreciating its growing customer base.
Related: MORE Power Iloilo Guide for Consumers

